TOBCO is proud to announce that they have recently completed the installation and commissioning of a triple chamber substation in St Leonards for Hutchinson Builders.
Over the past few months TOBCO have undertaken works such as; earthing grid installation, Conduit set out, metal work install, electrical fit out including protection wiring and optical arc flash protection, terminations, jointing and all and civil works associated with the project.
The scope of work includes a total of 100 street lights which will be maintained under three different authorities; TfNSW, Essential Energy and Eurobodalla Council.
The room was successfully commissioned powering 2 customer MSBs which will supply “The Landmark” building in St Leonards.
Business Owners Sam Turnbull & Glen O’Brien said “Well done to our Sydney team delivering this project for Hutchinson’s Builder. This project demonstrates TOBCOs unique ability to deliver Civil and Electrical works.
TOBCO will be working hard in the following years to continue to grow the Utilities business to ensure it is one of the strong performers in its five core business units